Aark Developers is building 1 project and 131 homes in Dubai.

Updated 27 Oct 2026
Handover record1 completed
0of 1 on time

Handed over within 3 months of the promised date. The typical project finished 6 quarters late. Too few dated handovers to rate as a share yet.

0on time1late
Projects underway1#247 in Dubai
Homes underway131#241 in Dubai

Projects. 1 underway, 1 delivered.

Aark TerracesDubai Residence Complex131Few salesQ2 2028promisedDubai Residence Complex · 131 homes
Aark ResidencesDubai Residence Complex1001,170May 20266 quarters lateDubai Residence Complex · 100 homes · 1,170/sqft

Median paid is every registered home sale in the project from Jul 2025 to Jun 2026, off-plan and resale; under 10 sales it reads few sales. Handover is the completion date declared on the register, and for a completed project the month of its first ready-market sale.

Where it builds. Paid price against each area.

Liwan2 projects17% under the area2 projects · 1,170 vs 1,405
Aark DevelopersArea median

Median AED per sqft of registered home sales, Jul 2025 to Jun 2026: Aark Developers’projects in the area against every sale in the area. Areas with fewer than 10 of its sales are left out.

Questions.

Does Aark Developers hand over on time?

1 of its completed Dubai projects has a dated handover, and 0 of it came within 3 months of the completion date declared on the register. That is too few to rate as a share: Esto rates a developer's record from 10 dated handovers.

How many projects is Aark Developers building in Dubai?

1 project with 131 homes is under construction on the Dubai Land Department register, #247 in the city by projects and #241 by homes, and 1 project is completed. Every one is listed on this page.

Where do these figures come from?

Projects, homes and completion dates come from the Dubai Land Department project register (as of 28 Sep 2026). Prices are registered sale deeds, never a price list. A handover is dated by the first ready-market sale after off-plan sales opened, which trails the keys, so every lateness figure is a floor. Esto compiles the register as it is: nothing on this page is paid for, and a developer cannot change a figure or a rank.

Are you Aark Developers? Claim this profile to add your logo, cover photo and a sales contact.

Bought from Aark Developers? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.

Get the app