Citadel Tower

Deyaar · Dubai Water Canal, Al Wasl · 419 homes · Completed

A completed Deyaar project in Dubai Water Canal, Al Wasl: 419 homes, handed over in Jul 2010, two quarters after the Q1 2010 date on the register.

Updated 27 Oct 2026
Completed Jul 2010Two quarters after Q1 2010 on the register
419 homesBedroom mix not declared
Dubai Water Canal, Al WaslDubai Land Department project 45

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ1 2010Q3 20102 quarters late
Against the area. Median paid.
Dubai Water Canal2,999
Al Wasl3,107

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Citadel Tower handed over?

In Jul 2010, when the first ready-market sale was registered. The register declared completion for Q1 2010, so it handed over two quarters late.

Who built Citadel Tower?

Deyaar. The project is registered to Deyaar on the Dubai Land Department register, which lists 39 projects for the developer in Dubai, 10 of them under construction. 4 of its 24 dated handovers came within 3 months of the promised date.

How many homes are in Citadel Tower?

419, as counted on the Dubai Land Department register.