Dt 1

Ellington · Downtown Dubai · 133 homes · Completed

A completed Ellington project in Downtown Dubai: 133 homes, handed over in Jan 2021, three quarters after the Q1 2020 date on the register. Registered resales from Jul 2025 to Jun 2026 had a median of AED 2,059 per sqft, 12% above the launch quarter.

Updated 27 Oct 2026
Completed Jan 2021Three quarters after Q1 2020 on the register
133 homesStudios, 1, 2, 3 and 4+ bedrooms
Downtown DubaiDubai Land Department project 1797

Prices. Quarter by quarter since launch.

Launch quarter, Q2 2018AED 1,837/sqft
Median paid, Q2 2025AED 2,488/sqft
Sales, Jul 2025 to Jun 202614
Median paidLatest quarterLaunch quarter AED 1,837
1,5002,0002,500Q2 18: AED 1,837/sqft, 16 salesQ1 20: AED 1,620/sqft, 10 salesQ2 21: AED 1,690/sqft, 38 salesQ4 21: AED 2,036/sqft, 14 salesQ2 25: AED 2,488/sqft, 10 salesQ2 18Q3 19Q4 20Q1 22Q2 23Q3 24Q2 25
Every quarter as a table
QuarterMedian AED/sqftSales
Q2 20181,83716
Q1 20201,62010
Q2 20211,69038
Q4 20212,03614
Q2 20252,48810

Median AED per sqft of registered sales, off-plan and ready, through Q3 2026. Quarters with fewer than 10 sales are left out. The launch quarter is the first quarter with 10 or more sales.

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ1 2020Q1 20213 quarters latePrice / sqftAED 1,837AED 2,059+12% on launch, resale median
Against the area. Median paid.
Dt 12,059

31% under the Downtown Dubai median.

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Dt 1 handed over?

In Jan 2021, when the first ready-market sale was registered. The register declared completion for Q1 2020, so it handed over three quarters late.

What do homes in Dt 1 sell for?

From Jul 2025 to Jun 2026, 14 homes sold on the register at a median of AED 2,059 per sqft and AED 2.98M per home. By unit type: 2 BR AED 3.84M (10 sales). These are registered deeds, not the developer's price list.

Who built Dt 1?

Ellington. The project is registered to Ellington on the Dubai Land Department register, which lists 73 projects for the developer in Dubai, 38 of them under construction. 10 of its 25 dated handovers came within 3 months of the promised date.

How many homes are in Dt 1?

133, as counted on the Dubai Land Department register. The declared mix: 26 studios, 39 1 BR, 52 2 BR, 15 3 BR, 1 4+ BR.