Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13

District One · MBR City · 133 homes · Completed

A completed District One project in MBR City: 133 homes, handed over in Mar 2024, three quarters after the Q3 2023 date on the register. Registered resales from Jul 2025 to Jun 2026 had a median of AED 2,301 per sqft, 36% above the launch quarter.

Updated 27 Oct 2026
Completed Mar 2024Three quarters after Q3 2023 on the register
133 homes1, 2 and 3 bedrooms
MBR CityDubai Land Department project 2162

Prices. Quarter by quarter since launch.

Launch quarter, Q1 2020AED 1,690/sqft
Median paid, Q2 2025AED 2,216/sqft
Sales, Jul 2025 to Jun 202616
Median paidLatest quarterLaunch quarter AED 1,690
2,000Q1 20: AED 1,690/sqft, 18 salesQ2 20: AED 1,705/sqft, 92 salesQ3 20: AED 1,733/sqft, 12 salesQ2 23: AED 2,015/sqft, 12 salesQ3 23: AED 1,985/sqft, 10 salesQ1 24: AED 1,759/sqft, 15 salesQ2 25: AED 2,216/sqft, 10 salesQ1 20Q1 21Q1 22Q1 23Q1 24Q2 25
Every quarter as a table
QuarterMedian AED/sqftSales
Q1 20201,69018
Q2 20201,70592
Q3 20201,73312
Q2 20232,01512
Q3 20231,98510
Q1 20241,75915
Q2 20252,21610

Median AED per sqft of registered sales, off-plan and ready, through Q3 2026. Quarters with fewer than 10 sales are left out. The launch quarter is the first quarter with 10 or more sales.

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ3 2023Q1 20243 quarters latePrice / sqftAED 1,690AED 2,301+36% on launch, resale median
Against the area. Median paid.
Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 132,301

12% over the MBR City median.

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13 handed over?

In Mar 2024, when the first ready-market sale was registered. The register declared completion for Q3 2023, so it handed over three quarters late.

What do homes in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13 sell for?

From Jul 2025 to Jun 2026, 16 homes sold on the register at a median of AED 2,301 per sqft and AED 2.73M per home. By unit type: 2 BR AED 2.65M (5 sales), 3 BR AED 4.08M (7 sales). These are registered deeds, not the developer's price list.

Who built Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13?

District One. The project is registered to District One on the Dubai Land Department register, which lists 37 projects for the developer in Dubai, 1 of them under construction. 1 of its 23 dated handovers came within 3 months of the promised date.

How many homes are in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13?

133, as counted on the Dubai Land Department register. The declared mix: 59 1 BR, 43 2 BR, 30 3 BR.

Bought in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.