Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 28

District One · District One, MBR City · 31 homes · Completed

A completed District One project in District One, MBR City: 31 homes, handed over in Sep 2023, a quarter after the Q2 2023 date on the register.

Updated 27 Oct 2026
Completed Sep 2023A quarter after Q2 2023 on the register
31 homes1 and 2 bedrooms
District One, MBR CityDubai Land Department project 2253

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ2 2023Q3 20231 quarter late
Against the area. Median paid.
District One2,001

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 28 handed over?

In Sep 2023, when the first ready-market sale was registered. The register declared completion for Q2 2023, so it handed over a quarter late.

Who built Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 28?

District One. The project is registered to District One on the Dubai Land Department register, which lists 37 projects for the developer in Dubai, 1 of them under construction. 1 of its 23 dated handovers came within 3 months of the promised date.

How many homes are in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 28?

31, as counted on the Dubai Land Department register. The declared mix: 26 1 BR, 5 2 BR.

Bought in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 28? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.

Get the app