Xl Tower

DAMAC · Business Bay · 165 homes · Completed

A completed DAMAC project in Business Bay: 165 homes, handed over in Jun 2011, two quarters after the Q4 2010 date on the register.

Updated 27 Oct 2026
Completed Jun 2011Two quarters after Q4 2010 on the register
165 homesBedroom mix not declared
Business BayDubai Land Department project 416

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ4 2010Q2 20112 quarters late

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Xl Tower handed over?

In Jun 2011, when the first ready-market sale was registered. The register declared completion for Q4 2010, so it handed over two quarters late.

Who built Xl Tower?

DAMAC. The project is registered to DAMAC on the Dubai Land Department register, which lists 260 projects for the developer in Dubai, 120 of them under construction. 24 of its 67 dated handovers came within 3 months of the promised date.

How many homes are in Xl Tower?

165, as counted on the Dubai Land Department register.