Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 18

District One · MBR City · 31 homes · Completed

A completed District One project in MBR City: 31 homes, handed over in Jul 2023, two quarters after the Q4 2022 date on the register.

Updated 27 Oct 2026
Completed Jul 2023Two quarters after Q4 2022 on the register
31 homes1 and 2 bedrooms
MBR CityDubai Land Department project 2238

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ4 2022Q3 20232 quarters late

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 18 handed over?

In Jul 2023, when the first ready-market sale was registered. The register declared completion for Q4 2022, so it handed over two quarters late.

Who built Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 18?

District One. The project is registered to District One on the Dubai Land Department register, which lists 37 projects for the developer in Dubai, 1 of them under construction. 1 of its 23 dated handovers came within 3 months of the promised date.

How many homes are in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 18?

31, as counted on the Dubai Land Department register. The declared mix: 26 1 BR, 5 2 BR.

Bought in Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 18? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.