One Canal

DAMAC · Dubai Water Canal, Jumeirah · 44 homes · Under construction

A DAMAC project under construction in Dubai Water Canal, Jumeirah: 44 homes, 77% built, with completion promised for Q2 2025 on the register, a date that has passed.

Updated 27 Oct 2026
Due Q2 2025The promised date has passed
44 homes3 and 4+ bedrooms
Dubai Water Canal, JumeirahDubai Land Department project 2501

Promised vs today. Launch to today.

At launchTodayHandoverQ2 202577% builtpast the promised date
Against the area. Median paid.
Dubai Water Canal3,819

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When will One Canal be completed?

The register declares completion for Q2 2025, and the project is reported 77% built. That date has passed without a handover on the register. DAMAC's completed Dubai projects typically finished 2 quarters late.

Who built One Canal?

DAMAC. The project is registered to DAMAC on the Dubai Land Department register, which lists 260 projects for the developer in Dubai, 120 of them under construction. 24 of its 67 dated handovers came within 3 months of the promised date.

How many homes are in One Canal?

44, as counted on the Dubai Land Department register. The declared mix: 19 3 BR, 25 4+ BR.

Bought in One Canal? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.