234 projects on the Dubai Land Department register are still under construction after the completion date their developer declared. 53 have had no inspection raise their progress in six months or more.
Register as of 27 Oct 2026
Past their declared date234
More than a year late55
No progress in six months53
Stalled. No progress in six months or more.
ProjectDeveloperBuiltLast progressDeclared
The VillaMazaya55%Aug 201213 years latedeclared Sep 2013Mazaya · 55% built · last rise Aug 2012
Teema 1 & Teema 2Emaar9%Oct 201910 years latedeclared Jul 2016Emaar · 9% built · last rise Oct 2019
MaysanEmaar37%Oct 201510 years latedeclared Jul 2016Emaar · 37% built · last rise Oct 2015
Champions Tower2Not on Esto yet78%Mar 20179 years latedeclared Oct 2017Dubai Sports City · 78% built · last rise Mar 2017
Silver StallionsNot on Esto yet12%Mar 20168 years latedeclared Dec 2017Jumeirah Village Triangle · 12% built · last rise Mar 2016
Royal ManorNot on Esto yet78%Sep 20187 years latedeclared Dec 2018MBR City · 78% built · last rise Sep 2018
Living Legends Phase 7Tanmiyat92%Aug 20215 years latedeclared Sep 2021Tanmiyat · Living Legends · 92% built · last rise Aug 2021
Binghatti AmberhallBinghatti38%Apr 20268 months latedeclared Feb 2026Binghatti · Jumeirah Village Circle · 38% built · last rise Apr 2026
Pier 8Pier 8 Real Estate Development LLC70%Feb 20247 months latedeclared Mar 2026Pier 8 Real Estate Development LLC · Dubai Marina · 70% built · last rise Feb 2024
Pelagos By IgoInvest Group Overseas84%Apr 20267 months latedeclared Mar 2026Invest Group Overseas · Dubai Marina · 84% built · last rise Apr 2026
Imperial ResidenceImperial 5543%Jan 20266 months latedeclared Apr 2026Imperial 55 · Dubai Production City · 43% built · last rise Jan 2026
77 Boulevard By BamBam Eskan Real Estate18%Mar 20261 month latedeclared Sep 2026Bam Eskan Real Estate · Jumeirah Village Circle · 18% built · last rise Mar 2026
Sahara LivingsNot on Esto yet93%Aug 202813 years latedeclared Jun 2013Dubai Industrial City · 93% built · at this pace Aug 2028
South LivingDubai South89%Jan 20276 years latedeclared Feb 2020Dubai South · Dubai South · 89% built · at this pace Jan 2027
The Heart Of EuropeThe Heart of Europe82%Mar 20474 years latedeclared Sep 2022The Heart of Europe · The World Islands · 82% built · at this pace Mar 2047
Damac CityDAMAC73%Sep 202710 months latedeclared Dec 2025DAMAC · Al Wasl · 73% built · at this pace Sep 2027
Q Gardens LoftsAYS Property Development91%Aug 202710 months latedeclared Dec 2025AYS Property Development · Jumeirah Village Circle · 91% built · at this pace Aug 2027
Verdana (Phase 1)Reportage95%Feb 202710 months latedeclared Dec 2025Reportage · Dubai Investment Park · 95% built · at this pace Feb 2027
Maimoon GardensFakhruddin Properties78%Jul 202710 months latedeclared Dec 2025Fakhruddin Properties · Jumeirah Village Circle · 78% built · at this pace Jul 2027
Verdana(Phase 2)Reportage94%Jan 202710 months latedeclared Dec 2025Reportage · Dubai Investment Park · 94% built · at this pace Jan 2027
Verdana ResidenceReportage96%Dec 202610 months latedeclared Dec 2025Reportage · Dubai Investment Park · 96% built · at this pace Dec 2026
Damac Lagoons - IbizaDAMAC79%Sep 202710 months latedeclared Dec 2025DAMAC · Damac Lagoons · 79% built · at this pace Sep 2027
Damac Lagoons - MykonosDAMAC81%Sep 202710 months latedeclared Dec 2025DAMAC · Damac Lagoons · 81% built · at this pace Sep 2027
Damac Lagoons - Monte CarloDAMAC86%May 202710 months latedeclared Dec 2025DAMAC · Damac Lagoons · 86% built · at this pace May 2027
Damac Lagoons - MarbellaDAMAC87%Apr 202710 months latedeclared Dec 2025DAMAC · Damac Lagoons · 87% built · at this pace Apr 2027
Sky Suites By Peace HomesPeace Homes56%Aug 202810 months latedeclared Dec 2025Peace Homes · Jumeirah Village Circle · 56% built · at this pace Aug 2028
The RingsPMR Property35%Nov 202910 months latedeclared Dec 2025PMR Property · Jumeirah · 35% built · at this pace Nov 2029
Azizi Venice 3Azizi76%Sep 202710 months latedeclared Dec 2025Azizi · Dubai South · 76% built · at this pace Sep 2027
Azizi Venice 4Azizi62%May 202810 months latedeclared Dec 2025Azizi · Dubai South · 62% built · at this pace May 2028
Azizi Venice 2Azizi57%Feb 203010 months latedeclared Dec 2025Azizi · Dubai South · 57% built · at this pace Feb 2030
Azizi Venice 1Azizi67%Sep 202810 months latedeclared Dec 2025Azizi · Dubai South · 67% built · at this pace Sep 2028
Aria By BeyondOmniyat85%Mar 20279 months latedeclared Jan 2026Omniyat · Dubai Maritime City · 85% built · at this pace Mar 2027
Azizi Venice 7Azizi29%Jun 20329 months latedeclared Jan 2026Azizi · Dubai South · 29% built · at this pace Jun 2032
The GrandalaPalladium Development86%Jan 20279 months latedeclared Jan 2026Palladium Development · Al Satwa · 86% built · at this pace Jan 2027
Mag 777Not on Esto yet67%Dec 20289 months latedeclared Jan 2026Dubai Sports City · 67% built · at this pace Dec 2028
Keturah ResortMAG15%Aug 20498 months latedeclared Feb 2026MAG · Bur Dubai · 15% built · at this pace Aug 2049
Binghatti RubyBinghatti65%Sep 20278 months latedeclared Feb 2026Binghatti · Jumeirah Village Circle · 65% built · at this pace Sep 2027
Niki Lauda TowerPreatoni0%Mar 21887 months latedeclared Mar 2026Preatoni · Business Bay · 0% built · at this pace Mar 2188
One CrescentAHS Properties80%Mar 20277 months latedeclared Mar 2026AHS Properties · Palm Jumeirah · 80% built · at this pace Mar 2027
Samana Waves 2Samana52%Jun 20287 months latedeclared Mar 2026Samana · Jumeirah Village Circle · 52% built · at this pace Jun 2028
Uh West By EllingtonEllington71%Jul 20277 months latedeclared Mar 2026Ellington · Jumeirah Heights · 71% built · at this pace Jul 2027
Uh East By EllingtonEllington47%Sep 20287 months latedeclared Mar 2026Ellington · Jumeirah Heights · 47% built · at this pace Sep 2028
The QuaysideEllington55%Jan 20287 months latedeclared Mar 2026Ellington · Business Bay · 55% built · at this pace Jan 2028
Sportz By DanubeDanube80%Apr 20277 months latedeclared Mar 2026Danube · Dubai Sports City · 80% built · at this pace Apr 2027
Roma Residences By JrpJRP Development77%Apr 20277 months latedeclared Mar 2026JRP Development · Jumeirah Village Circle · 77% built · at this pace Apr 2027
Lua ResidencesSwank Developments64%Feb 20287 months latedeclared Mar 2026Swank Developments · Meydan · 64% built · at this pace Feb 2028
Palatium ResidencesAhmadyar Developments88%Jan 20277 months latedeclared Mar 2026Ahmadyar Developments · Jumeirah Village Circle · 88% built · at this pace Jan 2027
161 Jumeirah LaneJAD Global70%Jun 20277 months latedeclared Mar 2026JAD Global · Al Satwa · 70% built · at this pace Jun 2027
Binghatti StarlightBinghatti63%Sep 20277 months latedeclared Mar 2026Binghatti · Bur Dubai · 63% built · at this pace Sep 2027
Samana MykonosSamana91%Feb 20276 months latedeclared Apr 2026Samana · Dubai Studio City · 91% built · at this pace Feb 2027
Samana Mykonos SignatureSamana86%Mar 20276 months latedeclared Apr 2026Samana · Arjan · 86% built · at this pace Mar 2027
Samana SkyrosSamana71%Jul 20276 months latedeclared Apr 2026Samana · Arjan · 71% built · at this pace Jul 2027
Eywa DubaiR. Evolution66%Nov 20276 months latedeclared Apr 2026R. Evolution · Business Bay · 66% built · at this pace Nov 2027
Elysee HeightsPantheon Development81%Mar 20276 months latedeclared Apr 2026Pantheon Development · Jumeirah Village Circle · 81% built · at this pace Mar 2027
Rove Home Residences By IrthIRTH63%Nov 20276 months latedeclared Apr 2026IRTH · Downtown Dubai · 63% built · at this pace Nov 2027
Parkwood ResidencesArabian Gulf Properties57%Oct 20296 months latedeclared Apr 2026Arabian Gulf Properties · Jumeirah Village Circle · 57% built · at this pace Oct 2029
Dalmore TowerDalmore Development95%Dec 20266 months latedeclared Apr 2026Dalmore Development · Liwan · 95% built · at this pace Dec 2026
W1Malina W1 Real Estate Development70%Jan 20286 months latedeclared Apr 2026Malina W1 Real Estate Development · Al Furjan · 70% built · at this pace Jan 2028
South Bay 2Dubai South94%Jan 20275 months latedeclared May 2026Dubai South · Dubai South · 94% built · at this pace Jan 2027
Terrazzo ResidencesTaraf Properties95%Dec 20265 months latedeclared May 2026Taraf Properties · Jumeirah Village Circle · 95% built · at this pace Dec 2026
Azizi Venice 14Azizi30%Feb 20305 months latedeclared May 2026Azizi · Dubai South · 30% built · at this pace Feb 2030
One By BinghattiBinghatti50%Sep 20285 months latedeclared May 2026Binghatti · Business Bay · 50% built · at this pace Sep 2028
Estrella By NexusNexus Developer46%Nov 20285 months latedeclared May 2026Nexus Developer · Majan · 46% built · at this pace Nov 2028
Alma GardensAlma Developments50%Mar 20285 months latedeclared May 2026Alma Developments · Liwan · 50% built · at this pace Mar 2028
Violet TowerDubai Investments Real Estate70%Jun 20274 months latedeclared Jun 2026Dubai Investments Real Estate · Jumeirah Village Circle · 70% built · at this pace Jun 2027
Floarea VistaMashriq Elite Developments63%Aug 20274 months latedeclared Jun 2026Mashriq Elite Developments · Discovery Gardens · 63% built · at this pace Aug 2027
Urban LifeUrban Properties Development80%Apr 20274 months latedeclared Jun 2026Urban Properties Development · Business Bay · 80% built · at this pace Apr 2027
Skyhills II By HreHRE Development96%Dec 20264 months latedeclared Jun 2026HRE Development · Jumeirah Village Circle · 96% built · at this pace Dec 2026
Skyhills III By HreHRE Development76%Jun 20274 months latedeclared Jun 2026HRE Development · Jumeirah Village Circle · 76% built · at this pace Jun 2027
Haven Bay ResidencesMetac Properties83%Feb 20274 months latedeclared Jun 2026Metac Properties · Dubai Islands · 83% built · at this pace Feb 2027
Enso JadeEnso Development42%Sep 20284 months latedeclared Jun 2026Enso Development · Al Satwa · 42% built · at this pace Sep 2028
Enso AmberEnso Development11%Mar 20414 months latedeclared Jun 2026Enso Development · Al Satwa · 11% built · at this pace Mar 2041
Evergrin HouseObject 155%Jan 20284 months latedeclared Jun 2026Object 1 · Al Satwa · 55% built · at this pace Jan 2028
Belle Reve By ZimayaZimaya Properties81%Apr 20272 months latedeclared Aug 2026Zimaya Properties · Jumeirah Village Circle · 81% built · at this pace Apr 2027
Iluka ResidencesMs Homes Development57%Dec 20272 months latedeclared Aug 2026Ms Homes Development · Dubai Islands · 57% built · at this pace Dec 2027
Jardin AstralGalaxy Realty45%Jun 20282 months latedeclared Aug 2026Galaxy Realty · Al Satwa · 45% built · at this pace Jun 2028
Rose Gardens 2Roz Real Estate Development51%Oct 20272 months latedeclared Aug 2026Roz Real Estate Development · Jumeirah Village Circle · 51% built · at this pace Oct 2027
City Center ResidencesDarglobal72%Oct 20301 month latedeclared Sep 2026Darglobal · Downtown Dubai · 72% built · at this pace Oct 2030
Ag SquareAG Properties69%Jan 20281 month latedeclared Sep 2026AG Properties · Liwan · 69% built · at this pace Jan 2028
Lanai IslandMajid Al Futtaim61%Dec 20271 month latedeclared Sep 2026Majid Al Futtaim · Tilal Al Ghaf · 61% built · at this pace Dec 2027
Kyoto By Oro24Oro24 Developments17%Mar 20351 month latedeclared Sep 2026Oro24 Developments · Arjan · 17% built · at this pace Mar 2035
Exotica By Al MarinaAl Marina Holding41%Jan 20311 month latedeclared Sep 2026Al Marina Holding · Jumeirah Village Circle · 41% built · at this pace Jan 2031
Minati Homes 1Januss Developer51%Jul 20281 month latedeclared Sep 2026Januss Developer · Al Furjan · 51% built · at this pace Jul 2028
Sereno ResidencesSvarn Development22%Oct 20311 month latedeclared Sep 2026Svarn Development · Jumeirah Village Circle · 22% built · at this pace Oct 2031
Havelock HeightsHMB Properties40%Oct 20281 month latedeclared Sep 2026HMB Properties · Jumeirah Village Circle · 40% built · at this pace Oct 2028
Ocean TowerNot on Esto yet30%Apr 20301 month latedeclared Sep 2026Dubai Islands · 30% built · at this pace Apr 2030
Built is the register’s percentage today. Last progress is the inspection that last raised it. At this pace carries the last year’s inspections forward from today. Declared is the completion date on the register.
Questions.
What counts as late?
A project is on this list when the register still has it under construction (Active) and the month of the completion date it declared is behind us. A project due this month is not on it yet. The declared date is the one on the register, which developers rarely move: it is not a sales brochure's handover date.
What does stalled mean?
The Dubai Land Department inspects projects under construction and records the percentage built, with the date. Stalled means no inspection has raised that percentage in six months or more. A project close to 100% can read as stalled while it waits for its completion certificate.
How is the finish month worked out?
From the pace of the register's own inspections over the last year: the percentage points gained, per month, carried forward from today. It is an extrapolation, not a promise, and it is left out for a stalled project or where the inspections span less than three months.
How often is this updated?
Esto takes a snapshot of the whole register every day and keeps every change it sees. This page was built from the snapshot of 27 Oct 2026.