Deyaar · Dubai Silicon Oasis · 717 homes · Under construction

A Deyaar project under construction in Dubai Silicon Oasis: 717 homes, 94% built, with completion promised for Q2 2025 on the register, a date that has passed. Registered off-plan sales from Jul 2025 to Jun 2026 had a median of AED 1,303 per sqft, 22% above the launch quarter.

Updated 27 Oct 2026
Due Q2 2025The promised date has passed
717 homesStudios, 1, 2 and 3 bedrooms
Dubai Silicon OasisDubai Land Department project 2403

Prices. Quarter by quarter since launch.

Launch quarter, Q4 2022AED 1,068/sqft
Median paid, Q3 2026AED 1,323/sqft
Sales, Jul 2025 to Jun 202693
Median paidLatest quarterLaunch quarter AED 1,068
1,0001,2001,400Q4 22: AED 1,068/sqft, 164 salesQ1 23: AED 1,090/sqft, 148 salesQ2 23: AED 1,070/sqft, 102 salesQ3 23: AED 1,064/sqft, 58 salesQ4 23: AED 1,027/sqft, 24 salesQ1 24: AED 1,062/sqft, 168 salesQ2 24: AED 1,040/sqft, 72 salesQ3 24: AED 1,105/sqft, 24 salesQ4 24: AED 1,152/sqft, 31 salesQ1 25: AED 1,163/sqft, 24 salesQ2 25: AED 1,202/sqft, 24 salesQ3 25: AED 1,272/sqft, 22 salesQ4 25: AED 1,303/sqft, 38 salesQ1 26: AED 1,372/sqft, 22 salesQ2 26: AED 1,375/sqft, 11 salesQ3 26: AED 1,323/sqft, 20 salesQ4 22Q3 23Q2 24Q1 25Q4 25Q3 26
Every quarter as a table
QuarterMedian AED/sqftSales
Q4 20221,068164
Q1 20231,090148
Q2 20231,070102
Q3 20231,06458
Q4 20231,02724
Q1 20241,062168
Q2 20241,04072
Q3 20241,10524
Q4 20241,15231
Q1 20251,16324
Q2 20251,20224
Q3 20251,27222
Q4 20251,30338
Q1 20261,37222
Q2 20261,37511
Q3 20261,32320

Median AED per sqft of registered sales, off-plan and ready, through Q3 2026. Quarters with fewer than 10 sales are left out. The launch quarter is the first quarter with 10 or more sales.

Promised vs today. Launch to today.

At launchTodayHandoverQ2 202594% builtpast the promised datePrice / sqftAED 1,068AED 1,303+22% on launch, off-plan median
Against the area. Median paid.
Tria By Deyaar1,303

1% over the Dubai Silicon Oasis median.

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When will Tria By Deyaar be completed?

The register declares completion for Q2 2025, and the project is reported 94% built. That date has passed without a handover on the register. Deyaar's completed Dubai projects typically finished 3 quarters late.

What do homes in Tria By Deyaar sell for?

From Jul 2025 to Jun 2026, 93 homes sold on the register at a median of AED 1,303 per sqft and AED 985K per home. By unit type: Studio AED 630K (32 sales), 1 BR AED 1M (38 sales), 2 BR AED 1.61M (20 sales). These are registered deeds, not the developer's price list.

Who built Tria By Deyaar?

Deyaar. The project is registered to Deyaar on the Dubai Land Department register, which lists 39 projects for the developer in Dubai, 10 of them under construction. 4 of its 24 dated handovers came within 3 months of the promised date.

How many homes are in Tria By Deyaar?

717, as counted on the Dubai Land Department register. The declared mix: 180 studios, 300 1 BR, 192 2 BR, 39 3 BR.

Bought in Tria By Deyaar? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.