Trillium Heights
Grenorbit · Al Satwa · 56 homes · Under construction
A Grenorbit project under construction in Al Satwa: 56 homes, 62% built, with completion promised for Q4 2025 on the register, a date that has passed.
Updated 27 Oct 2026Promised vs today. Launch to today.
The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.
Questions.
When will Trillium Heights be completed?
The register declares completion for Q4 2025, and the project is reported 62% built. That date has passed without a handover on the register.
Who built Trillium Heights?
Grenorbit. The project is registered to Grenorbit on the Dubai Land Department register, which lists 1 project for the developer in Dubai, 1 of them under construction.
How many homes are in Trillium Heights?
56, as counted on the Dubai Land Department register. The declared mix: 16 studios, 40 1 BR.