Smart Heights

DAMAC · Barsha Heights (Tecom) · 205 homes · Completed

A completed DAMAC project in Barsha Heights (Tecom): 205 homes, handed over in Aug 2011, three quarters after the Q4 2010 date on the register.

Updated 27 Oct 2026
Completed Aug 2011Three quarters after Q4 2010 on the register
205 homesBedroom mix not declared
Barsha Heights (Tecom)Dubai Land Department project 425

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ4 2010Q3 20113 quarters late

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Smart Heights handed over?

In Aug 2011, when the first ready-market sale was registered. The register declared completion for Q4 2010, so it handed over three quarters late.

Who built Smart Heights?

DAMAC. The project is registered to DAMAC on the Dubai Land Department register, which lists 260 projects for the developer in Dubai, 120 of them under construction. 24 of its 67 dated handovers came within 3 months of the promised date.

How many homes are in Smart Heights?

205, as counted on the Dubai Land Department register.