Starz Tower By Danube

Danube · Al Furjan · 454 homes · Completed

A completed Danube project in Al Furjan: 454 homes, handed over in Aug 2019, two quarters after the Q1 2019 date on the register. Registered resales from Jul 2025 to Jun 2026 had a median of AED 1,316 per sqft, 17% above the launch quarter.

Updated 27 Oct 2026
Completed Aug 2019Two quarters after Q1 2019 on the register
454 homesStudios, 1 and 2 bedrooms
Al FurjanDubai Land Department project 1699

Prices. Quarter by quarter since launch.

Launch quarter, Q2 2016AED 1,129/sqft
Median paid, Q4 2025AED 1,300/sqft
Sales, Jul 2025 to Jun 202648
Median paidLatest quarterLaunch quarter AED 1,129
1,000Q2 16: AED 1,129/sqft, 397 salesQ3 16: AED 1,140/sqft, 24 salesQ4 19: AED 841/sqft, 10 salesQ3 22: AED 835/sqft, 12 salesQ1 23: AED 901/sqft, 11 salesQ3 23: AED 1,025/sqft, 13 salesQ4 23: AED 1,038/sqft, 15 salesQ3 24: AED 1,237/sqft, 17 salesQ4 24: AED 1,233/sqft, 10 salesQ2 25: AED 1,187/sqft, 14 salesQ3 25: AED 1,318/sqft, 13 salesQ4 25: AED 1,300/sqft, 19 salesQ2 16Q1 18Q4 19Q3 21Q2 23Q4 25
Every quarter as a table
QuarterMedian AED/sqftSales
Q2 20161,129397
Q3 20161,14024
Q4 201984110
Q3 202283512
Q1 202390111
Q3 20231,02513
Q4 20231,03815
Q3 20241,23717
Q4 20241,23310
Q2 20251,18714
Q3 20251,31813
Q4 20251,30019

Median AED per sqft of registered sales, off-plan and ready, through Q3 2026. Quarters with fewer than 10 sales are left out. The launch quarter is the first quarter with 10 or more sales.

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ1 2019Q3 20192 quarters latePrice / sqftAED 1,129AED 1,316+17% on launch, resale median
Against the area. Median paid.
Starz Tower By Danube1,316

52% under the Al Furjan median.

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Starz Tower By Danube handed over?

In Aug 2019, when the first ready-market sale was registered. The register declared completion for Q1 2019, so it handed over two quarters late.

What do homes in Starz Tower By Danube sell for?

From Jul 2025 to Jun 2026, 48 homes sold on the register at a median of AED 1,316 per sqft and AED 560K per home. By unit type: Studio AED 540K (31 sales), 1 BR AED 860K (10 sales), 2 BR AED 1.16M (7 sales). These are registered deeds, not the developer's price list.

Who built Starz Tower By Danube?

Danube. The project is registered to Danube on the Dubai Land Department register, which lists 42 projects for the developer in Dubai, 23 of them under construction. 12 of its 19 dated handovers came within 3 months of the promised date.

How many homes are in Starz Tower By Danube?

454, as counted on the Dubai Land Department register. The declared mix: 270 studios, 120 1 BR, 56 2 BR.

Bought in Starz Tower By Danube? Track it against these numbers.

Esto keeps your payment plan, what is due, and how the area around it is moving.

Get the app