Talia Residences

Deyaar · Al Furjan · 160 homes · Completed

A completed Deyaar project in Al Furjan: 160 homes, handed over in Jul 2026, five quarters after the Q2 2025 date on the register.

Updated 27 Oct 2026
Completed Jul 2026Five quarters after Q2 2025 on the register
160 homes1 and 2 bedrooms
Al FurjanDubai Land Department project 2570

Promised vs delivered. Launch to today.

At launchDeliveredHandoverQ2 2025Q3 20265 quarters late

The promised date is the completion date declared on the Dubai Land Department register. A handover is dated by the first ready-market sale on the register, which trails the keys. The launch price is the launch quarter’s median of registered sales, not a brochure. Area medians are every registered home sale in the area, Jul 2025 to Jun 2026.

Questions.

When was Talia Residences handed over?

In Jul 2026, when the first ready-market sale was registered. The register declared completion for Q2 2025, so it handed over five quarters late.

Who built Talia Residences?

Deyaar. The project is registered to Deyaar on the Dubai Land Department register, which lists 39 projects for the developer in Dubai, 10 of them under construction. 4 of its 24 dated handovers came within 3 months of the promised date.

How many homes are in Talia Residences?

160, as counted on the Dubai Land Department register. The declared mix: 126 1 BR, 33 2 BR.